Thursday, May 7, 2015

Composite Risk Identification

Composite Risk Identification

The first step in creating a Composite Risk Plan is to identify the likely risks, which may affect the project.




 A series of risk categories is identified and for each category, a suite of potential risks is listed. This may take place during a ‘Risk Planning’ workshop, involving each of the key project stakeholders who are involved in / affected by the project. This may include the project sponsor, manager, team, suppliers, and in some cases, even the customer. Each of the risks identified is described in detail and documented within the Risk Plan.

Definition

Provide a formal definition for the term ‘risk’ for this project. For example:

“A risk is defined as any event which is likely to adversely affect the ability of the project to achieve the defined objectives”. ©

Categories

Identify the likely categories of risks for this project. Each risk category is a particular aspect of the project, which is likely to experience a risk during the lifecycle of the project. Examples of typical risk categories include:

·         Requirements
·         Benefits
·         Schedule
·         Budget
·         Deliverable
·         Scope
·         Issues
·         Supplier
·         Acceptance
·         Communication
·         Resource. ©

  Risks

Identify the likely risks for each category provided above by completing the following table. Each risk identified should be allocated a unique identifier (id) number.

Category©
Description
Id
Requirements
·       The requirements have not been clearly specified
·       The requirements specified do not match the customer's needs
·       The requirements specified are not measurable
1.1
1.2
1.3
Benefits
·       The business benefits have not been identified
·       The business benefits are not quantifiable
·       The final solution delivered does not achieve the required benefits
2.1
2.2
2.3
Schedule
·       The schedule doesn’t provide enough time to complete the project
·       The schedule doesn’t list all of the activities and tasks required
·       The schedule doesn’t provide accurate dependencies
3.1
3.2
3.3
Budget
·       The project exceeds the budget allocated
·       There is unaccounted expenditure on the project
·       There is no single resource accountable for recording budgeted spending
4.1
4.2
4.3
Deliverables
·       The deliverables required by the project are not clearly defined
·       Clear quality criteria for each deliverable have not been defined
·       The deliverable produced doesn’t meet the quality criteria defined
5.1
5.2
5.3
Scope
·       The scope of the project is not clearly outlined
·       The project is not undertaken within the agreed scope
·       Project changes negatively impact on the project
6.1
6.2
6.3
Issues
·       Project issues are not resolved within an appropriate timescale
·       Similar issues continually reappear throughout the project
·       Unresolved issues become new risks to the project
7.1
7.2
7.3
Suppliers
·       The expectations for supplier delivery are not defined
·       Suppliers do not meet the expectations defined
·       Supplier issues negatively impact on the project
8.1
8.2
8.3
Acceptance
·       The criteria for accepting project deliverables aren’t clearly defined
·       Customers do not accept the final deliverables of the project
·       The acceptance process leaves the customer dissatisfied
9.1
9.2
9.3
Communication
·       Lack of controlled communication causes project issues
·       Key project stakeholders are ‘left in the dark’ about progress
10.1
10.2
10.3
Resource
·       Staff allocated to the project are not suitably skilled
·       Insufficient equipment is available to undertake the project
·       There is a shortage of materials available when required
11.1
11.2
11.3

0 comments:

Post a Comment